大家好,有谁知道在ps进度分析过程中,有一种方法是里程碑计算POC,帮助文档里: If the fixed date of the milestone is reached, the planned
percentage of completion of the WBS element or the activity is set
to the percentage of completion which you entered for the milestone.

If the actual date of the milestone is reached, the actual
percentage of completion of the WBS element or the activity is set
to the percentage of completion which you entered for the milestone.
其中的reach是指计算机系统日期到里程碑的日期吗?